During the past weeks of February 5 & 12, the following work was accomplished on the Project:
- Illumination work, including light bases, cables, and poles, continued along Route 8 SB Exits 15 to 13, and on local roads.
- Pothole repair work continued along the entire Route 8 corridor both northbound (NB) and southbound (SB)
- Pipe lining work began throughout the Project limits on Route 8 NB and SB. See photos below.
For the weeks of February 19 & 26, we will continue:
- Illumination work on light bases, cables, and poles along Route 8 SB Exit 15 to 13, and on local roads
- Pothole repair work across the entire Route 8 corridor both NB and SB spanning from Exits 15 to 22.
- Lining of pipes throughout the Project corridor from Exits 15 to 22, both NB and SB.