Update for the Weeks of October 21 and 28, 2024

  1. Home
  2. Construction Alerts
  3. Update for the Weeks of October 21 and 28, 2024

Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.

Nighttime work will continue from 6PM to 6AM:

Nighttime operations will typically occur Sunday night through Thursday night.

  • Saw-cutting will continue, and concrete pavement repair activities will continue, northbound from Exit 15 to 22 (New Exits 12B to 18).
  • Night work milling, surveying, and paving has begun and will continue, in one-mile segments, with new pavement installed within two days.
  • Work will continue for approximately 1-2 more weeks southbound from Exit 23 to Exit 15 (New Exits 21 to 12B).

There is no upcoming Daytime work.

Previous Post
Update for the Weeks of October 7 and 14, 2024