Daytime work will continue (7AM – 3PM, Monday–Friday)
- Both northbound and southbound traffic lanes shifted to the right shoulder to create work areas for median barrier replacement between Exits 12b–15 (former Exits 16–19) and Exits 15-17(former Exits 19 and 21).
- Another median work zone will be established northbound and southbound between Exit 18 on and off ramps (former Exit 22)
- Median barrier and median drainage replacement are underway.
- Ramp and shoulder drainage repair will continue throughout northbound and southbound from Exits 12B–18 (former Exits 15–22).
Night work will continue (6PM – 6AM, Sunday–Thursday)
- Concrete pavement repair activities will resume Southbound from the Project limits at the North Main Street Bridge in Seymour to Exit 18 and Southbound from Exit 13-Exit 12b.
- Traffic pattern will remain the same (both directions shifted to the right shoulder).
- Median barrier and drainage work will continue.