During the past weeks of February 19 & 26, the following work was accomplished on the Project:
- Illumination work, including light bases, cables, and poles, continued along Route 8 SB Exits 14 to 13, and on local roads.
- Pipe lining work continued throughout the Project limits on Route 8 NB and SB and on local roads. See photos below.
For the weeks of March 4 & 11, we will continue:
- Illumination work on light bases, cables, and poles along Route 8 SB Exit 15 to 13, and on local roads.
- Pothole repair work across the entire Route 8 corridor both NB and SB spanning from Exits 15 to 22, as necessary.
- Lining of pipes throughout the Project corridor from Exits 15 to 22, both NB and SB and on local roads.