Nighttime work will continue from 6PM- 6AM:

  • Saw-cutting will continue, and concrete pavement repair activities will continue, northbound from Exit 15 to 22.

Daytime work will continue from 8AM to 3PM:

  • Illumination work along Route 8 southbound Exit 17 – 12, northbound from Exit 22 off-ramp to Exit 22 on-ramp.

Future activities:

  • In September, night work milling, surveying, and paving will begin again, in one-mile segments, with new pavement installed within two days. Work will continue northbound to Exit 23, then southbound from Exit 23 to Exit 15.