For the past weeks – December 4 through December 15 – we accomplished the following work:

  • The milling and paving operation on Route 8 between Exit 19-22 NB Northbound (NB) and Southbound (SB) has been completed as of 12/15.
  • Work on the illumination continued the past two weeks at Exit 14-13 SB and Exit 14-15 NB bridges.

Anticipated work for the week of December 18 is as follows: 

  • Continued illumination work at Exit 14-13 SB on light bases, cable, and poles and Exit 15-16 NB bridge cable.

No work will take place during the week of December 25. Work will resume the following week on January 2, 2024.

 

 