Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.
Nighttime work will continue from 6PM to 6AM:
- Nighttime operations will typically occur Sunday night through Thursday night.
- Saw-cutting and concrete pavement repair activities will continue, northbound from Exit 15 to 22 (New Exits 12B to 18).
- Both northbound and southbound traffic lanes have moved to the right shoulder to create a work area for median barrier replacement between Exit 20 and 22 (New Exits 17-18).
- Median barrier and median drainage is being replaced.