Nighttime work will continue as follows, from 6:00 PM to 6:00 AM:

  • Illumination work along Route 8 southbound from Exit 17 to 12, and northbound from the Exit 22 off-ramp to the Exit 22 on-ramp.
  • Saw-cutting will continue, and concrete pavement repair activities will continue, from Exit 15 to 22 northbound.

Future activities:

  • Beginning in August 2024, night work milling, surveying, and paving will begin again both north and south bound, in one-mile segments, with new pavement installed within two days.
  • This work began from the Exit 15 on-ramp and will continue northbound through Exit 22/23. Southbound work will then begin, starting from Exit 22/23 and continuing to the Exit 15 southbound off-ramp.

photo 6553689 reduced

Next Post
Update for the Weeks of July 29 & August 5, 2024