Work will continue as follows:
- Signage continues to be posted on the jobsite.
- Saw-cutting will begin June 10, and concrete pavement repair activities will begin June 17, from Exit 15 to 22 northbound.
Other work continuing throughout the project:
- Illumination work on along Route 8 southbound from Exit 17 to 12
Future activities:
- Beginning in August 2024, night work milling, surveying, and paving will begin again both north and south bound, in one-mile segments, with new pavement installed within two days.
- This work began from the Exit 15 on-ramp and will continue northbound through Exit 22/23. Southbound work will then begin, starting from Exit 22/23 and continuing to the Exit 15 southbound off-ramp.
img 9598