Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.

Nighttime work will continue from 6PM to 6AM:

  • Nighttime operations will typically occur Sunday night through Thursday night.
  • Saw-cutting will continue, and concrete pavement repair activities will continue, northbound from Exit 15 to 22 (New Exits 12B to 18).

Beginning November 11, 2024: Upcoming night work will include a period of 1-2 weeks to install a traffic shift for both lanes moving to the right shoulder to create a work area for upcoming barrier replacement. This will occur both northbound and southbound, between Exit 20 and 22 (New Exits 17-18).

There is no upcoming Daytime work.

Next Post
Update for the Weeks of November 18 & 25, 2024
Previous Post
Update for the Weeks of October 21 and 28, 2024