Update for the Weeks of October 7 and 14, 2024

  1. Home
  2. Construction Alerts
  3. Update for the Weeks of October 7 and 14, 2024

Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.

Nighttime work will continue from 6PM to 6AM:

  • Nighttime operations will typically occur Sunday night through Thursday night.
  • Saw-cutting will continue, and concrete pavement repair activities will continue, northbound from Exit 15 to 22.

There is no upcoming Daytime work.

Future activities:

Beginning October 6, night work milling, surveying, and paving will begin again, in one-mile segments, with new pavement installed within two days. Work will continue for approximately 2-3 weeks northbound to Exit 23, then southbound from Exit 23 to Exit 15.

 