This past week of April 17, we continued to:
- Perform drainage site investigations between Exits 15 and 22
- Perform work on Route 8, both northbound and southbound
- Implement temporary traffic patterns
During the weeks of April 24 – May 1, upcoming work is anticipated to be as follows:
- Drainage site investigation with anticipated completion by May 1
- Highway Illumination and Incident Management System (IMS) work anticipated to begin on May 1
- Illumination and IMS work will begin at Exit 17 and will commence southbound along the Route 8 corridor
- Work will take place during the daytime, with intermittent lane closures
Above: Northern limit of the project (Exit 22), looking south