During the past weeks of March 18 & 25, we accomplished the following work:
- Illumination work, including light bases, cables, and poles, continued along Route 8 SB Exits 13 to 12.
- Pipe lining work continued (see photos below) throughout the Project limits on Route 8 NB and SB and on local roads.
For the weeks of April 1 & 8, we will continue:
Day Shift:
-
- Illumination work on light bases, cables, and poles along Route 8 SB Exit 13 to 12.
Night Shift:
-
- Lining of pipes throughout the Project limits from Exits 15 to 22, both NB and SB and on local roads.
- Pothole repair work across Route 8 NB and SB spanning from Exits 15 to 22, as necessary.